Cost
Planning-level studies indicate that an effective combination of ICM strategies can be implemented for $7.5 Million per year (annualized capital and O&M).
September 2008
San Francisco,California,United States
Summary Information
- Capital Costs – Non-recurring (one-time) expenditure required to procure and install ITS equipment. These costs included the capital equipment costs as well as the soft costs required for design and installation.
- Operations and Maintenance (O&M) Costs – Recurring costs required to operate and maintain the deployed equipment, including labor costs. While these costs did contain provisions for upkeep and replacement of minor components of the system, they did not contain provisions for wholesale replacement of the equipment when it reached the end of its useful life. The O&M costs were presented as annual estimates.
- Annualized Costs – The capital and O&M costs of an ITS improvement amortized over its anticipated useful life time.
The Test Corridor ICM cost estimates below were derived from Table 5.2 and Appendix-A of the source report. The author noted that each of the strategies listed would require a traffic management center (TMC) and a good traffic detection system with coverage every one-half mile. The average costs reported were expressed in terms of net present value (published 2008).
| ICM Improvements | Average Annual Capital and O&M Costs ($ Millions) |
|---|---|
| Common Infrastructure | 1.4 |
| Arterial Traffic Signal Control | 1.8 |
| Local Adaptive Ramp Metering | 1.5 |
| Highway Traveler Information | 1.0 |
| Transit Traveler Information | 0.7 |
| HOT lanes | 2.1 |
| Combination of ICM Strategies | 7.5 |
| Equipment | Useful life (Years) | Capital Cost | Annual O&M Cost | Annualized Lifecycle Costs Infrastructure | Annualized Lifecycle Costs Incremental | Unit | Amount | Total Annual Cost |
|---|---|---|---|---|---|---|---|---|
| Common Infrastructure (Basic Needs): $1.4 Million | ||||||||
| Basic TMC Facilities | $633,333 | $633,333 | ||||||
| Hardware/Software for Traffic Surveillance | 20 | $150,000 | $7,500 | $15,000 | $15,000 | |||
| Loop Detector System Integration | $25,000 | $25,000 | ||||||
| Loop Detector (double set) | $3,350 | ea ½-mi | 120 | $402,000 | ||||
| DS3 Communication Line | $2,700 | ea ½-mi | 120 | $324,000 | ||||
| Arterial Traffic Signal Control: $1.8 Million | ||||||||
| Linked Signal System LAN | 20 | $55,000 | $1,100 | $3,850 | $3,850 | |||
| TMC Hardware for Signal Control | 5 | $22,500 | $2,000 | $6,500 | $6,500 | |||
| TMC Software/System Integration | 5 | $200,000 | $40,000 | $40,000 | ||||
| Labor for Arterial Mgmt* | $540,000 | $540,000 | $540,000 | |||||
| Signal Controller Upgrade | 20 | $6,250 | $350 | $663 | per int | 160 | $106,000 | |
| DS1 Communication Line | 20 | $750 | $6,600 | $6,638 | per int | 160 | $1,062,000 | |
| Ramp Metering (Fixed or Adaptive): $1.5 Million | ||||||||
| Ramp Meter (Signal, Controller) | 5 | $40,000 | $2,000 | $10,000 | per ramp | 90 | $900,000 | |
| Loop Detectors (2) | 5 | $11,000 | $4,500 | $6,700 | per ramp | 90 | $603,000 | |
| Highway Traveler Information: $1.0 Million | ||||||||
| TMC Hardware for Info Dissemination | 5 | $7,500 | $375 | $1,875 | $1,875 | |||
| TMC Software for Info Dissemination | 5 | $20,000 | $1,000 | $5,000 | $5,000 | |||
| TMC System Integration | 20 | $100,000 | $5,000 | $10,000 | $10,000 | |||
| DS3 Communication Line | 20 | $4,000 | $48,000 | $48,200 | $48,200 | |||
| Labor for Information Dissemination* | $100,000 | $100,000 | ||||||
| Information Service Center Hardware | 20 | $45,000 | $900 | $3,150 | $3,150 | |||
| Info Center System Integration | 5 | $100,000 | $20,000 | $20,000 | ||||
| Information Service Center Software | $34,375 | $34,375 | ||||||
| Map Database Software | 2 | $22,500 | $11,250 | $11,250 | ||||
| Information Service Center Labor* | $225,000 | $225,000 | ||||||
| DS0 Communication Line | $938 | per CMS | 32 | $30,000 | ||||
| Changeable Message Sign | $9,025 | per CMS | 32 | $288,800 | ||||
| Changeable Message Sign Tower | $6,525 | per CMS | 32 | $208,800 | ||||
| Transit Traveler Information $0.7 Million | ||||||||
| TMC Information Dissemination Hardware | 5 | $7,500 | $375 | $1,875 | $1,875 | |||
| TMC Information Dissemination Software | 5 | $20,000 | $1,000 | $5,000 | $5,000 | |||
| TMC System Integration | 20 | $100,000 | $5,000 | $10,000 | $10,000 | |||
| Labor for Traffic Info Dissemination* | $100,000 | $100,000 | $100,000 | |||||
| DS3 Communication Line | 20 | $4,000 | $48,000 | $48,200 | $48,200 | |||
| Transit Center Hardware | 10 | $22,500 | $2,250 | $2,250 | ||||
| Transit Center Software/Integration | 20 | $815,000 | $9,000 | $49,750 | $49,750 | |||
| Transit Center Labor* | $150,000 | $150,000 | $150,000 | |||||
| DS3 Communication Line | 20 | $4,000 | $48,000 | $48,200 | $48,200 | |||
| Information Service Center Hardware | 20 | $45,000 | $900 | $3,150 | $3,150 | |||
| Info Center System Integration | 5 | $100,000 | $20,000 | $20,000 | ||||
| Information Service Center Software | 20 | $412,000 | $20,625 | $41,225 | $41,225 | |||
| Map Database Software | 2 | $22,500 | $11,250 | $11,250 | ||||
| Information Service Center Labor* | $225,000 | $225,000 | $225,000 | |||||
| HOT Lanes: $2.1 Million | ||||||||
| Electronic Toll Collection Software | 10 | $20,000 | $2,000 | $2,000 | ||||
| Electronic Toll Collection Structure | 20 | $30,000 | $1,500 | $1,500 | ||||
| Software for Dynamic Electronic Tolls | $9,120 | $9,120 | ||||||
| Integration for Dynamic Electronic Tolls | $14,650 | $14,650 | ||||||
| Labor for HOT Lanes Mgmt* | $540,000 | $540,000 | $540,000 | |||||
| Electronic Toll Reader | 10 | $10,000 | $1,000 | $2,000 | ea ½-mi | 120 | $240,000 | |
| High-Speed Camera | 10 | $20,000 | $2,000 | $4,000 | ea ½-mi | 120 | $480,000 | |
| DS1 Communication Line | 20 | $750 | $6,600 | $6,638 | ea ½-mi | 120 | $796,500 | |
| Combination of ICM Strategies: $7.5 Million | ||||||||
| Basic TMC Facilities | $633,333 | $633,333 | ||||||
| Hardware/Software for traffic Surveillance | 20 | $150,000 | $7,500 | $15,000 | $15,000 | |||
| Loop Detector System Integration | $25,000 | $25,000 | ||||||
| Loop Detector (double set) | $3,350 | ea ½-mi | 120 | $402,000 | ||||
| DS3 Communication Line | $2,700 | ea ½-mi | 120 | $324,000 | ||||
| Linked Signal System LAN | 20 | $55,000 | $1,100 | $3,850 | $3,850 | |||
| TMC Hardware for Signal Control | 5 | $22,500 | $2,000 | $6,500 | $6,500 | |||
| TMC Software/System Integration | 5 | $200,000 | $40,000 | $40,000 | ||||
| Labor for Arterial Mgmt* | $540,000 | $540,000 | $540,000 | |||||
| Signal Controller Upgrade | 20 | $6,250 | $350 | $663 | per int | 160 | $106,000 | |
| DS1 Communication Line | 20 | $750 | $6,000 | $6,638 | per int | 160 | $1,062,000 | |
| Ramp Meter (Signal, Controller) | 5 | $40,000 | $2,000 | $10,000 | per ramp | 90 | $900,000 | |
| Loop Detectors (2) | 5 | $11,000 | $4,500 | $6,700 | per ramp | 90 | $603,000 | |
| TMC Information Dissemination Hardware | 5 | $7,500 | $375 | $1,875 | $1,875 | |||
| TMC Information Dissemination Software | 5 | $20,000 | $1,000 | $5,000 | $5,000 | |||
| TMC System Integration | 20 | $100,000 | $5,000 | $10,000 | $10,000 | |||
| Labor for Traffic Info Dissemination* | $100,000 | $100,000 | $100,000 | |||||
| DS3 Communication Line | 20 | $4,000 | $48,000 | $48,200 | $48,200 | |||
| Transit Center Hardware | 10 | $22,500 | $2,250 | $2,250 | ||||
| Transit Center Software/Integration | 20 | $815,000 | $9,000 | $49,750 | $49,750 | |||
| Transit Center Labor* | $150,000 | $150,000 | $150,000 | |||||
| DS3 Communication Line | 20 | $4,000 | $48,000 | $48,200 | $48,200 | |||
| Information Service Center Hardware | 20 | $45,000 | $900 | $3,150 | $3,150 | |||
| Info Center System Integration | 5 | $100,000 | $20,000 | $20,000 | ||||
| Information Service Center Software | 20 | $412,000 | $20,625 | $41,225 | $41,225 | |||
| Map Database Software | 2 | $22,500 | $11,250 | $11,250 | ||||
| Information Service Center Labor* | $225,000 | $225,000 | $225,000 | |||||
| Electronic Toll Collection Software | 10 | $20,000 | $2,000 | $2,000 | ||||
| Electronic Toll Collection Structure | 20 | $30,000 | $1,500 | $1,500 | ||||
| Software for Dynamic Electronic Tolls | 5 | $55,000 | $2,700 | $13,700 | ||||
| Integration for Dynamic Electronic Tolls | 20 | $220,000 | $11,000 | $22,000 | ||||
| Labor for HOT Lanes Mgmt* | $540,000 | $540,000 | $540,000 | |||||
| Electronic Toll Reader | 10 | $10,000 | $1,000 | $2,000 | ea ½-mi | 120 | $240,000 | |
| High-Speed Camera | $4,000 | ea ½-mi | 120 | $480,000 | ||||
| DS1 Communication Line | $6,638 | ea ½-mi | 120 | $796,500 | ||||
The author noted that significant cost savings may be realized through the sharing of equipment and integration of deployed components.
Notes:
Related Benefits Database summary: "Integrated Approach: Inside story on the ICM test corridor," Traffic Technology International 2009.
Application Areas
Intelligent Transportation Systems > Freeway Management > Lane Management > Pricing
Intelligent Transportation Systems > Freeway Management > Lane Management > High-Occupancy Vehicle Facilities
Intelligent Transportation Systems > Freeway Management > Ramp Control > Ramp Metering
Intelligent Transportation Systems > Freeway Management > Information Dissemination > Dynamic Message Signs
Intelligent Transportation Systems > Arterial Management > Traffic Control > Adaptive Signal Control
Intelligent Transportation Systems > Arterial Management > Information Dissemination > Dynamic Message Signs
Intelligent Transportation Systems > Traveler Information > En Route Information > Wireless
Intelligent Transportation Systems > Traveler Information > Pre-Trip Information > Internet/Wireless
Intelligent Transportation Systems > Traffic Incident Management > Information Dissemination > Dynamic Message Signs
Intelligent Transportation Systems > Transit Management > Information Dissemination > Internet/Wireless/Phone
Intelligent Transportation Systems > Transportation Management Centers > Permanent TMCs > Freeway
Intelligent Transportation Systems > Transportation Management Centers > Permanent TMCs > Arterial
Intelligent Transportation Systems > Transportation Management Centers > Permanent TMCs > Transit
Related Unit Cost Subsystems
Roadside Telecommunications (RS-TC)
Roadside Detection (RS-D)
Roadside Control (RS-C)
Roadside Information (RS-I)
Toll Plaza (TP)
Remote Location (RM)
Information Service Provider (ISP)
Transportation Management Center (TM)
Transit Management Center (TR)
Commercial Vehicle Electronic Credentialing (EC)/Administration
Keywords
congestion pricing, value pricing, variable road pricing, managed lanes, high occupancy vehicles, carpool lanes, high occupancy vehicle lane, HOV, ramp meters, DMS, CMS, VMS, Changeable Message Signs, Variable Message Signs, traffic signals, adaptive signals