Follow a modular approach when deploying complex projects in locations with a shortened construction season.
Experience from the Integrated Corridor Traffic Management Project in Minnesota
April 2000
Minneapolis,Minnesota,United States
Background (Show)
Lesson Learned
The purpose of the ICTM technologies was to balance traffic flow and capacity at the corridor level through the adaptive control of traffic signals and ramps, and to improve incident management strategies through a motorist information system. Deployed systems included an adaptive traffic control system for arterial traffic signals and freeway metered ramps, a queue detection system to prevent queue spillover from the metered ramps onto the adjacent streets, an incident management system including 11 arterial closed-circuit television (CCTV) cameras, and a motorist information system including trailblazing and dynamic message signs for the purpose of diverting local and regional traffic.
In addition to estimating the benefits of the deployment, the evaluators identified lessons learned on the ICTM strategy of deployment and contracting, which include the following.
- Consider a modular approach to deployment in which the deployment proceeds in separate sections. The project was deployed in four modules across a 5-year span. The complexity of the project in combination with the shortened construction season in Minnesota warranted deploying the project in four modules in 5 years, from 1994 to 2000. Following the modular approach to deployment had a couple of key advantages. First, each module had a set of manageable goals that enabled a concentrated work effort for achieving specific outcomes. Second, it allowed project staff to learn how to operate the new systems incrementally, and for project managers to apply lessons learned from prior module deployments to subsequent ones.
- Beware that there are risks, in addition to advantages, associated with a modular deployment. The experience of the ICTM project showed that using a modular approach extended the deployment schedule, which led to stakeholders losing interest in the project over time (when other projects and issues arose that demanded their attention). In addition, the longer deployment period increased the difficulties and costs of the evaluation. For example, during the ICTM deployment period from 1994 to 2000, other improvements and changes occurred along the corridor, such as the construction of new streets and housing complexes, replaced traffic signals, and increases in traffic volume, all of which reduced the capability of reaching firm conclusions about the effects of the ICTM. Lastly, an extended deployment schedule increases the risk of funding interruptions and delays (which happened in the ICTM project).
- Consider the option of using different contract mechanisms for subsystems in a complex project. Complex projects often use the design-build and/or the design-bid-build type of contracts. In a design-build contract, the transportation agency uses the services of one entity (e.g., a consulting firm or in-house staff) for the design and construction of a system. The agency invites contractors to submit bids and then manages the contractors. In contrast, in the design-bid-build mechanism, the transportation agency contracts with separate entities to do work on different elements of a project. To deliver the various components of the ICTM, the ICTM management successfully used both design-bid-build and design-build procurement mechanisms. Although the project primarily used a design-bid-build mechanism, it employed a design-build mechanism for the motorist information system. A design-build strategy was appropriate for the motorist information system because it was not commercially available as an off-the-shelf product, and it required a comprehensive development of features and functions unique to the ICTM.
To manage the deployment of a complex project in a region with a shortened construction season, the ICTM project followed a modular approach. The approach also had the benefit of allowing management the opportunity to apply lessons learned during the deployment of one module to the next. The ICTM also employed both design-bid-build and design-build contract vehicles, depending on the needs of the particular subsystem. These deployment strategies, which enabled the ICTM partnership to complete the ICTM project, are worthy of consideration by transportation agencies that are preparing for or managing complex transportation improvement projects.
Application Areas
Intelligent Transportation Systems > Traffic Incident Management > Information Dissemination > Dynamic Message Signs
Intelligent Transportation Systems > Traffic Incident Management > Surveillance & Detection > Imaging/Video
Intelligent Transportation Systems > Freeway Management > Ramp Control > Ramp Metering
Intelligent Transportation Systems > Arterial Management > Traffic Control > Advanced Signal Systems
Intelligent Transportation Systems > Arterial Management > Surveillance > Traffic
Intelligent Transportation Systems > Freeway Management > Information Dissemination > Dynamic Message Signs
Intelligent Transportation Systems > Traffic Incident Management > Surveillance & Detection > Imaging/Video
Intelligent Transportation Systems > Traffic Incident Management > Information Dissemination > Dynamic Message Signs
Intelligent Transportation Systems > Freeway Management > Surveillance > Traffic
Intelligent Transportation Systems > Freeway Management > Ramp Control > Ramp Metering
Intelligent Transportation Systems > Freeway Management > Information Dissemination > Dynamic Message Signs
Intelligent Transportation Systems > Arterial Management > Traffic Control > Adaptive Signal Control
Intelligent Transportation Systems > Arterial Management > Information Dissemination > Dynamic Message Signs
States
Countries
Systems Engineering
Focus Areas
Major Initiatives > Cooperative Intersection Collision Avoidance Systems
Major Initiatives > Integrated Corridor Management Systems
Major Initiatives > Nationwide Surface Transportation Weather Observing and Forecasting System - Clarus
Major Initiatives > Emergency Transportation Operations
Other Program Activities > Amber Alert
Other Program Activities > Public Safety
Other Program Activities > Rural ITS Deployment
Goal Areas
Keywords
DMS, CMS, VMS, Changeable Message Signs, Variable Message Signs, CCTV, closed circuit television cameras, road monitoring, camera imaging, ramp meters, coordinated signals, signal coordination, centralized signal control, signal synchronization, traffic signals, advanced signal control, signal timing optimization, coordinated signal control, advanced signal controller, traffic signal retiming, retiming, sensors, vehicle detector, traffic detection, traffic monitoring, congestion monitoring, adaptive signals

Lesson Comments
No comments posted to date