Unit Costs (Adjusted)
Equipment Costs for Toll Plaza (TP)
Note: Equipment list adjusted to 2009 dollars. The date in parentheses under the capital cost value and O&M cost value represents the dollar year from which the cost value was adjusted. All costs are in $K.
| Unit Cost Element | IDAS # | Life Years |
Capital Cost $K, 2009 Dollars (Source Year) |
O&M Cost $K/year, Dollars (Source Year) |
Description |
|---|---|---|---|---|---|
| Electronic Toll Reader Index: 2 | TP001 | 10 | 2 - 4 (2001) | 0.2 - 0.4 (2001) | Readers (per lane). O&M is estimated at 10% of capital cost. |
| High-Speed Camera Index: 2 | TP002 | 10 | 6 - 8 (2003) | 0.3 - 0.7 (1995) | Cost includes one camera per two lanes. |
| Electronic Toll Collection Software Index: 3 | TP003 | 10 | 5 - 10 (1995) | Includes COTS software and database. | |
| Electronic Toll Collection Structure Index: 4 | TP004 | 20 | 14 - 22 (1995) | Mainline structure. | |
| Other Unit Cost Elements Index: - | - | - | - | - | Summary values under development |