| Unit Cost Element | Unit Cost Component | Description | Location | Cost Type | Data Date | Reported Units | Units | Year (Dollars) | Capital Cost Per Unit | O& M Cost Per Unit | Lifetime (Years) | View Details |
| Conduit Design and Installation - Corridor | Communication design | Locate system electronic equipment, transmitter | Florida, United States | Estimated | 2013 | | Each (EA) | 2013 | $4,610.50 | | | View Details |
| Conduit Design and Installation - Corridor | Communications design | Locate system electronic equipment, receiver | Florida, United States | Estimated | 2013 |  | Each (EA) | 2013 | $5,000.00 |  |  | View Details |
| Conduit Design and Installation - Corridor | Communications design | Locate system electronic equipment, box marker | Florida, United States | Estimated | 2013 | | Each (EA) | 2013 | $101.90 | | | View Details |
| Conduit Design and Installation - Corridor | Conduit | Electrical Conduit (2 inch PVC) and Trenching | Phoenix, Arizona, USA | Estimated | 2009 |  | Per Mile | 2009 | $58,080.00 |  |  | View Details |
| Conduit Design and Installation - Corridor | Conduit | Electrical Conduit (2 inch PVC) and Trenching | Phoenix, Arizona, USA | Actual | 2009 | | Per Mile | 2009 | $50,160.00 | | | View Details |
| Conduit Design and Installation - Corridor | Conduit | Electrical Conduit (2 inch PVC) and Trenching | Phoenix, Arizona, USA | Actual | 2009 |  | Per Mile | 2009 | $36,960.00 |  |  | View Details |
| Conduit Design and Installation - Corridor | Conduit | Electrical Conduit (2 inch PVC) and Trenching | Phoenix, Arizona, USA | Actual | 2009 | | Per Mile | 2009 | $10,560.00 | | | View Details |
| Conduit Design and Installation - Corridor | Conduit | Electrical Conduit (2 inch PVC) and Trenching | Phoenix, Arizona, USA | Actual | 2009 |  | Per Mile | 2009 | $50,160.00 |  |  | View Details |
| Conduit Design and Installation - Corridor | Conduit | Electrical Conduit (2 inch PVC) | Phoenix, Arizona, USA | Actual | 2009 | | Per Mile | 2009 | $18,480.00 | | | View Details |
| Conduit Design and Installation - Corridor | Conduit | Electrical Conduit (2.5 inch PVC) and Trenching | Phoenix, Arizona, USA | Estimated | 2009 | 240 | Linear Foot (LF) | 2009 | $24.00 |  |  | View Details |
| Conduit Design and Installation - Corridor | Conduit | Electrical Conduit (2.5 inch PVC) and Trenching | Phoenix, Arizona, USA | Actual | 2009 | 240 | Linear Foot (LF) | 2009 | $10.00 | | | View Details |
| Conduit Design and Installation - Corridor | Conduit | Electrical Conduit (2.5 inch PVC) and Trenching | Phoenix, Arizona, USA | Actual | 2009 | 240 | Linear Foot (LF) | 2009 | $8.00 |  |  | View Details |
| Conduit Design and Installation - Corridor | Conduit | Electrical Conduit (2.5 inch PVC) and Trenching | Phoenix, Arizona, USA | Actual | 2009 | 240 | Linear Foot (LF) | 2009 | $23.00 | | | View Details |
| Conduit Design and Installation - Corridor | Conduit | Electrical Conduit (2.5 inch PVC) and Trenching | Phoenix, Arizona, USA | Actual | 2009 | 240 | Linear Foot (LF) | 2009 | $10.50 |  |  | View Details |
| Conduit Design and Installation - Corridor | Conduit | Electrical Conduit (2.5 inch PVC) and Trenching | Phoenix, Arizona, USA | Actual | 2009 | 240 | Linear Foot (LF) | 2009 | $17.78 | | | View Details |
| Conduit Design and Installation - Corridor | Conduit | Electrical Conduit (3 inch PVC or HDPE) and Trenching | Phoenix, Arizona, USA | Estimated | 2009 |  | Per Mile | 2009 | $95,040.00 |  |  | View Details |
| Conduit Design and Installation - Corridor | Conduit | Electrical Conduit (3 inch PVC or HDPE) and Trenching | Phoenix, Arizona, USA | Actual | 2009 | | Per Mile | 2009 | $52,800.00 | | | View Details |
| Conduit Design and Installation - Corridor | Conduit | Electrical Conduit (3 inch PVC or HDPE) and Trenching | Phoenix, Arizona, USA | Actual | 2009 |  | Per Mile | 2009 | $47,520.00 |  |  | View Details |
| Conduit Design and Installation - Corridor | Conduit | Electrical Conduit (3 inch PVC or HDPE) and Trenching | Phoenix, Arizona, USA | Actual | 2009 | | Per Mile | 2009 | $95,040.00 | | | View Details |
| Conduit Design and Installation - Corridor | Conduit | Electrical Conduit (3 inch PVC or HDPE) and Trenching | Phoenix, Arizona, USA | Actual | 2009 |  | Per Mile | 2009 | $58,080.00 |  |  | View Details |
| Conduit Design and Installation - Corridor | Conduit | Electrical Conduit (3 inch PVC or HDPE) and Trenching | Phoenix, Arizona, USA | Actual | 2009 | | Per Mile | 2009 | $58,713.60 | | | View Details |
| Conduit Design and Installation - Corridor | Conduit | Electrical Conduit (2-3 inch PVC) and Trenching | Phoenix, Arizona, USA | Actual | 2009 |  | Per Mile | 2009 | $73,920.00 |  |  | View Details |
| Conduit Design and Installation - Corridor | Conduit | Electrical Conduit (2-3 inch PVC) and Trenching | Phoenix, Arizona, USA | Actual | 2009 | | Per Mile | 2009 | $50,160.00 | | | View Details |
| Conduit Design and Installation - Corridor | Conduit | Electrical Conduit (2-3 inch PVC) and Trenching | Phoenix, Arizona, USA | Actual | 2009 |  | Per Mile | 2009 | $55,440.00 |  |  | View Details |
| Conduit Design and Installation - Corridor | Conduit | Electrical Conduit (2-3 inch PVC) and Trenching | Phoenix, Arizona, USA | Actual | 2009 | | Per Mile | 2009 | $73,920.00 | | | View Details |
| Conduit Design and Installation - Corridor | Conduit | Electrical Conduit (2-3 inch PVC) and Trenching | Phoenix, Arizona, USA | Actual | 2009 |  | Per Mile | 2009 | $52,800.00 |  |  | View Details |
| Conduit Design and Installation - Corridor | Conduit | Electrical Conduit (2-3 inch PVC) and Trenching | Phoenix, Arizona, USA | Actual | 2009 | | Per Mile | 2009 | $42,134.40 | | | View Details |
| Conduit Design and Installation - Corridor | Conduit | Electrical Conduit (2-3 inch HDPE) and Directional Drilling | Phoenix, Arizona, USA | Estimated | 2009 |  | Per Mile | 2009 | $190,080.00 |  |  | View Details |
| Conduit Design and Installation - Corridor | Conduit | Electrical Conduit (2-3 inch HDPE) and Directional Drilling | Phoenix, Arizona, USA | Actual | 2009 | | Per Mile | 2009 | $147,840.00 | | | View Details |
| Conduit Design and Installation - Corridor | Conduit | Electrical Conduit (2-3 inch HDPE) and Directional Drilling | Phoenix, Arizona, USA | Actual | 2009 |  | Per Mile | 2009 | $129,360.00 |  |  | View Details |
| Conduit Design and Installation - Corridor | Conduit | Electrical Conduit (2-3 inch HDPE) and Directional Drilling | Phoenix, Arizona, USA | Actual | 2009 | | Per Mile | 2009 | $184,800.00 | | | View Details |
| Conduit Design and Installation - Corridor | Conduit | Electrical Conduit (2-3 inch HDPE) and Directional Drilling | Phoenix, Arizona, USA | Actual | 2009 |  | Per Mile | 2009 | $84,480.00 |  |  | View Details |
| Conduit Design and Installation - Corridor | Conduit | Electrical Conduit (2-3 inch HDPE) and Directional Drilling | Phoenix, Arizona, USA | Actual | 2009 | | Per Mile | 2009 | $79,780.80 | | | View Details |
| Conduit Design and Installation - Corridor | Conduit | Electrical Conduit (3-3 inch HDPE) and Directional Drilling | Phoenix, Arizona, USA | Estimated | 2009 | 220 | Linear Foot (LF) | 2009 | $50.00 |  |  | View Details |
| Conduit Design and Installation - Corridor | Conduit | Electrical Conduit (3-3 inch HDPE) and Directional Drilling | Phoenix, Arizona, USA | Actual | 2009 | 220 | Linear Foot (LF) | 2009 | $45.00 | | | View Details |
| Conduit Design and Installation - Corridor | Conduit | Electrical Conduit (3-3 inch HDPE) and Directional Drilling | Phoenix, Arizona, USA | Actual | 2009 | 220 | Linear Foot (LF) | 2009 | $26.00 |  |  | View Details |
| Conduit Design and Installation - Corridor | Conduit | Electrical Conduit (3-3 inch HDPE) and Directional Drilling | Phoenix, Arizona, USA | Actual | 2009 | 220 | Linear Foot (LF) | 2009 | $43.00 | | | View Details |
| Conduit Design and Installation - Corridor | Conduit | Electrical Conduit (3-3 inch HDPE) and Directional Drilling | Phoenix, Arizona, USA | Actual | 2009 | 220 | Linear Foot (LF) | 2009 | $20.00 |  |  | View Details |
| Conduit Design and Installation - Corridor | Conduit | Electrical Conduit (3-3 inch HDPE) and Directional Drilling | Phoenix, Arizona, USA | Actual | 2009 | 220 | Linear Foot (LF) | 2009 | $18.43 | | | View Details |
| Conduit Design and Installation - Corridor | Conduit | Electrical Conduit (3 inch PVC) and Directional Drilling | Phoenix, Arizona, USA | Estimated | 2009 |  | Per Mile | 2009 | $66,000.00 |  |  | View Details |
| Conduit Design and Installation - Corridor | Conduit | Electrical Conduit (3 inch PVC) and Directional Drilling | Phoenix, Arizona, USA | Actual | 2009 | | Per Mile | 2009 | $50,160.00 | | | View Details |
| Conduit Design and Installation - Corridor | Conduit | Electrical Conduit (3 inch PVC) and Directional Drilling | Phoenix, Arizona, USA | Actual | 2009 |  | Per Mile | 2009 | $42,240.00 |  |  | View Details |
| Conduit Design and Installation - Corridor | Conduit | Electrical Conduit (3 inch PVC) and Directional Drilling | Phoenix, Arizona, USA | Actual | 2009 | | Per Mile | 2009 | $105,600.00 | | | View Details |
| Conduit Design and Installation - Corridor | Conduit | Electrical Conduit (3 inch PVC) and Directional Drilling | Phoenix, Arizona, USA | Actual | 2009 |  | Per Mile | 2009 | $50,160.00 |  |  | View Details |
| Conduit Design and Installation - Corridor | Conduit | Electrical Conduit (3 inch PVC) and Directional Drilling | Phoenix, Arizona, USA | Actual | 2009 | | Per Mile | 2009 | $33,633.60 | | | View Details |
| Conduit Design and Installation - Corridor | Conduit | Electrical Conduit (3 inch HDPE) and Directional Drilling | Phoenix, Arizona, USA | Estimated | 2009 | 500 | Linear Foot (LF) | 2009 | $35.00 |  |  | View Details |
| Conduit Design and Installation - Corridor | Conduit | Electrical Conduit (3 inch HDPE) and Directional Drilling | Phoenix, Arizona, USA | Actual | 2009 | 500 | Linear Foot (LF) | 2009 | $29.00 | | | View Details |
| Conduit Design and Installation - Corridor | Conduit | Electrical Conduit (3 inch HDPE) and Directional Drilling | Phoenix, Arizona, USA | Actual | 2009 | 500 | Linear Foot (LF) | 2009 | $22.00 |  |  | View Details |
| Conduit Design and Installation - Corridor | Conduit | Electrical Conduit (3 inch HDPE) and Directional Drilling | Phoenix, Arizona, USA | Actual | 2009 | 500 | Linear Foot (LF) | 2009 | $32.00 | | | View Details |
| Conduit Design and Installation - Corridor | Conduit | Electrical Conduit (3 inch HDPE) and Directional Drilling | Phoenix, Arizona, USA | Actual | 2009 | 500 | Linear Foot (LF) | 2009 | $13.50 |  |  | View Details |
| Conduit Design and Installation - Corridor | Conduit | Electrical Conduit (3 inch HDPE) and Directional Drilling | Phoenix, Arizona, USA | Actual | 2009 | 500 | Linear Foot (LF) | 2009 | $14.70 | | | View Details |
| Conduit Design and Installation - Corridor | Conduit | Electrical Conduit (3-3 inch HDPE) and Directional Drilling | Phoenix, Arizona, USA | Estimated | 2009 |  | Per Mile | 2009 | $84,480.00 |  |  | View Details |
| Conduit Design and Installation - Corridor | Conduit | Electrical Conduit (3-3 inch HDPE) and Directional Drilling | Phoenix, Arizona, USA | Actual | 2009 | | Per Mile | 2009 | $68,640.00 | | | View Details |
| Conduit Design and Installation - Corridor | Conduit | Electrical Conduit (3-3 inch HDPE) and Directional Drilling | Phoenix, Arizona, USA | Actual | 2009 |  | Per Mile | 2009 | $71,280.00 |  |  | View Details |
| Conduit Design and Installation - Corridor | Conduit | Electrical Conduit (3-3 inch HDPE) and Directional Drilling | Phoenix, Arizona, USA | Actual | 2009 | | Per Mile | 2009 | $89,760.00 | | | View Details |
| Conduit Design and Installation - Corridor | Conduit | Electrical Conduit (3-3 inch HDPE) and Directional Drilling | Phoenix, Arizona, USA | Actual | 2009 |  | Per Mile | 2009 | $52,800.00 |  |  | View Details |
| Conduit Design and Installation - Corridor | Conduit | Electrical Conduit (3-3 inch HDPE) and Directional Drilling | Phoenix, Arizona, USA | Actual | 2009 | | Per Mile | 2009 | $51,374.40 | | | View Details |
| Conduit Design and Installation - Corridor | Conduit | Electrical Conduit (4-3 inch PVC) and Directional Drilling | Phoenix, Arizona, USA | Estimated | 2009 | 130 | Linear Foot (LF) | 2009 | $25.00 |  |  | View Details |
| Conduit Design and Installation - Corridor | Conduit | Electrical Conduit (4-3 inch PVC) and Directional Drilling | Phoenix, Arizona, USA | Actual | 2009 | 130 | Linear Foot (LF) | 2009 | $26.00 | | | View Details |
| Conduit Design and Installation - Corridor | Conduit | Electrical Conduit (4-3 inch PVC) and Directional Drilling | Phoenix, Arizona, USA | Actual | 2009 | 130 | Linear Foot (LF) | 2009 | $16.00 |  |  | View Details |
| Conduit Design and Installation - Corridor | Conduit | Electrical Conduit (4-3 inch PVC) and Directional Drilling | Phoenix, Arizona, USA | Actual | 2009 | 130 | Linear Foot (LF) | 2009 | $20.00 | | | View Details |
| Conduit Design and Installation - Corridor | Conduit | Electrical Conduit (4-3 inch PVC) and Directional Drilling | Phoenix, Arizona, USA | Actual | 2009 | 130 | Linear Foot (LF) | 2009 | $11.50 |  |  | View Details |
| Conduit Design and Installation - Corridor | Conduit | Electrical Conduit (4-3 inch PVC) and Directional Drilling | Phoenix, Arizona, USA | Actual | 2009 | 130 | Linear Foot (LF) | 2009 | $15.44 | | | View Details |
| Conduit Design and Installation - Corridor | Conduit | 1.25 inch conduit. Includes directional drilling at $13 per linear foot. | North Carolina, United States | Bid Tabulation | 2006 |  | LF | 2006 | $18.25 |  |  | View Details |
| Conduit Design and Installation - Corridor | Conduit | ELECTRICAL CONDUIT (2") (PVC) (OR HDPE) | Tucson, Arizona, United States | Estimated | 2009 | 200 | Linear Foot (LF) | 2009 | $7.00 | | | View Details |
| Conduit Design and Installation - Corridor | Conduit | ELECTRICAL CONDUIT (2") (PVC) (OR HDPE) | Tucson, Arizona, United States | Actual | 2009 | 200 | Linear Foot (LF) | 2009 | $3.80 |  |  | View Details |
| Conduit Design and Installation - Corridor | Conduit | ELECTRICAL CONDUIT (2") (PVC) (OR HDPE) | Tucson, Arizona, United States | Estimated | 2009 | 200 | Linear Foot (LF) | 2009 | $6.95 | | | View Details |
| Conduit Design and Installation - Corridor | Conduit | ELECTRICAL CONDUIT (2") (PVC) (OR HDPE) | Tucson, Arizona, United States | Estimated | 2009 | 200 | Linear Foot (LF) | 2009 | $7.00 |  |  | View Details |
| Conduit Design and Installation - Corridor | Conduit | ELECTRICAL CONDUIT (2") (PVC) (OR HDPE) | Tucson, Arizona, United States | Estimated | 2009 | 200 | Linear Foot (LF) | 2009 | $9.00 | | | View Details |
| Conduit Design and Installation - Corridor | Conduit | ELECTRICAL CONDUIT (2") (PVC) (OR HDPE) | Tucson, Arizona, United States | Estimated | 2009 | 200 | Linear Foot (LF) | 2009 | $9.00 |  |  | View Details |
| Conduit Design and Installation - Corridor | Conduit | ELECTRICAL CONDUIT (2") (PVC) (OR HDPE) | Tucson, Arizona, United States | Estimated | 2009 | 200 | Linear Foot (LF) | 2009 | $4.75 | | | View Details |
| Conduit Design and Installation - Corridor | Conduit | ELECTRICAL CONDUIT (2") (PVC) (OR HDPE) | Tucson, Arizona, United States | Estimated | 2009 | 200 | Linear Foot (LF) | 2009 | $5.00 |  |  | View Details |
| Conduit Design and Installation - Corridor | Conduit | ELECTRICAL CONDUIT (2") (PVC) (OR HDPE) | Tucson, Arizona, United States | Estimated | 2009 | 200 | Linear Foot (LF) | 2009 | $9.80 | | | View Details |
| Conduit Design and Installation - Corridor | Conduit | ELECTRICAL CONDUIT (2 1/2") (PVC) | Tucson, Arizona, United States | Estimated | 2009 | 40 | Linear Foot (LF) | 2009 | $15.00 |  |  | View Details |
| Conduit Design and Installation - Corridor | Conduit | ELECTRICAL CONDUIT (2 1/2") (PVC) | Tucson, Arizona, United States | Actual | 2009 | 40 | Linear Foot (LF) | 2009 | $4.20 | | | View Details |
| Conduit Design and Installation - Corridor | Conduit | ELECTRICAL CONDUIT (2 1/2") (PVC) | Tucson, Arizona, United States | Estimated | 2009 | 40 | Linear Foot (LF) | 2009 | $7.23 |  |  | View Details |
| Conduit Design and Installation - Corridor | Conduit | ELECTRICAL CONDUIT (2 1/2") (PVC) | Tucson, Arizona, United States | Estimated | 2009 | 40 | Linear Foot (LF) | 2009 | $15.00 | | | View Details |
| Conduit Design and Installation - Corridor | Conduit | ELECTRICAL CONDUIT (2 1/2") (PVC) | Tucson, Arizona, United States | Estimated | 2009 | 40 | Linear Foot (LF) | 2009 | $33.00 |  |  | View Details |
| Conduit Design and Installation - Corridor | Conduit | ELECTRICAL CONDUIT (2 1/2") (PVC) | Tucson, Arizona, United States | Estimated | 2009 | 40 | Linear Foot (LF) | 2009 | $9.00 | | | View Details |
| Conduit Design and Installation - Corridor | Conduit | ELECTRICAL CONDUIT (2 1/2") (PVC) | Tucson, Arizona, United States | Estimated | 2009 | 40 | Linear Foot (LF) | 2009 | $5.50 |  |  | View Details |
| Conduit Design and Installation - Corridor | Conduit | ELECTRICAL CONDUIT (2 1/2") (PVC) | Tucson, Arizona, United States | Estimated | 2009 | 40 | Linear Foot (LF) | 2009 | $26.00 | | | View Details |
| Conduit Design and Installation - Corridor | Conduit | ELECTRICAL CONDUIT (2 1/2") (PVC) | Tucson, Arizona, United States | Estimated | 2009 | 40 | Linear Foot (LF) | 2009 | $10.26 |  |  | View Details |
| Conduit Design and Installation - Corridor | Conduit | ELECTRICAL CONDUIT (3") (PVC) (OR HDPE) | Tucson, Arizona, United States | Estimated | 2009 | | Per Mile | 2009 | $38,520.00 | | | View Details |
| Conduit Design and Installation - Corridor | Conduit | ELECTRICAL CONDUIT (3") (PVC) (OR HDPE) | Tucson, Arizona, United States | Actual | 2009 |  | Per Mile | 2009 | $17,976.00 |  |  | View Details |
| Conduit Design and Installation - Corridor | Conduit | ELECTRICAL CONDUIT (3") (PVC) (OR HDPE) | Tucson, Arizona, United States | Estimated | 2009 | | Per Mile | 2009 | $34,240.00 | | | View Details |
| Conduit Design and Installation - Corridor | Conduit | ELECTRICAL CONDUIT (3") (PVC) (OR HDPE) | Tucson, Arizona, United States | Estimated | 2009 |  | Per Mile | 2009 | $29,960.00 |  |  | View Details |
| Conduit Design and Installation - Corridor | Conduit | ELECTRICAL CONDUIT (3") (PVC) (OR HDPE) | Tucson, Arizona, United States | Estimated | 2009 | | Per Mile | 2009 | $47,080.00 | | | View Details |
| Conduit Design and Installation - Corridor | Conduit | ELECTRICAL CONDUIT (3") (PVC) (OR HDPE) | Tucson, Arizona, United States | Estimated | 2009 |  | Per Mile | 2009 | $38,520.00 |  |  | View Details |
| Conduit Design and Installation - Corridor | Conduit | ELECTRICAL CONDUIT (3") (PVC) (OR HDPE) | Tucson, Arizona, United States | Estimated | 2009 | | Per Mile | 2009 | $27,820.00 | | | View Details |
| Conduit Design and Installation - Corridor | Conduit | ELECTRICAL CONDUIT (3") (PVC) (OR HDPE) | Tucson, Arizona, United States | Estimated | 2009 |  | Per Mile | 2009 | $38,520.00 |  |  | View Details |
| Conduit Design and Installation - Corridor | Conduit | ELECTRICAL CONDUIT (3") (PVC) (OR HDPE) | Tucson, Arizona, United States | Estimated | 2009 | | Per Mile | 2009 | $39,547.20 | | | View Details |
| Conduit Design and Installation - Corridor | Conduit | ELECTRICAL CONDUIT (2-3") (PVC) (OR HDPE) | Tucson, Arizona, United States | Estimated | 2009 |  | Per Mile | 2009 | $94,160.00 |  |  | View Details |
| Conduit Design and Installation - Corridor | Conduit | ELECTRICAL CONDUIT (2-3") (PVC) (OR HDPE) | Tucson, Arizona, United States | Actual | 2009 | | Per Mile | 2009 | $25,252.00 | | | View Details |
| Conduit Design and Installation - Corridor | Conduit | ELECTRICAL CONDUIT (2-3") (PVC) (OR HDPE) | Tucson, Arizona, United States | Estimated | 2009 |  | Per Mile | 2009 | $35,096.00 |  |  | View Details |
| Conduit Design and Installation - Corridor | Conduit | ELECTRICAL CONDUIT (2-3") (PVC) (OR HDPE) | Tucson, Arizona, United States | Estimated | 2009 | | Per Mile | 2009 | $25,680.00 | | | View Details |
| Conduit Design and Installation - Corridor | Conduit | ELECTRICAL CONDUIT (2-3") (PVC) (OR HDPE) | Tucson, Arizona, United States | Estimated | 2009 |  | Per Mile | 2009 | $89,880.00 |  |  | View Details |
| Conduit Design and Installation - Corridor | Conduit | ELECTRICAL CONDUIT (2-3") (PVC) (OR HDPE) | Tucson, Arizona, United States | Estimated | 2009 | | Per Mile | 2009 | $42,800.00 | | | View Details |
| Conduit Design and Installation - Corridor | Conduit | ELECTRICAL CONDUIT (2-3") (PVC) (OR HDPE) | Tucson, Arizona, United States | Estimated | 2009 |  | Per Mile | 2009 | $44,726.00 |  |  | View Details |
| Conduit Design and Installation - Corridor | Conduit | ELECTRICAL CONDUIT (2-3") (PVC) (OR HDPE) | Tucson, Arizona, United States | Estimated | 2009 | | Per Mile | 2009 | $42,800.00 | | | View Details |
| Conduit Design and Installation - Corridor | Conduit | ELECTRICAL CONDUIT (2-3") (PVC) (OR HDPE) | Tucson, Arizona, United States | Estimated | 2009 |  | Per Mile | 2009 | $42,671.60 |  |  | View Details |
| Conduit Design and Installation - Corridor | Conduit | ELECTRICAL CONDUIT (2-3" HDPE, DIRECTIONAL DRILL) | Tucson, Arizona, United States | Estimated | 2009 | 450 | Linear Foot (LF) | 2009 | $30.00 | | | View Details |
| Conduit Design and Installation - Corridor | Conduit | ELECTRICAL CONDUIT (2-3" HDPE, DIRECTIONAL DRILL) | Tucson, Arizona, United States | Actual | 2009 | 450 | Linear Foot (LF) | 2009 | $16.70 |  |  | View Details |
| Conduit Design and Installation - Corridor | Conduit | ELECTRICAL CONDUIT (2-3" HDPE, DIRECTIONAL DRILL) | Tucson, Arizona, United States | Estimated | 2009 | 450 | Linear Foot (LF) | 2009 | $18.61 | | | View Details |
| Conduit Design and Installation - Corridor | Conduit | ELECTRICAL CONDUIT (2-3" HDPE, DIRECTIONAL DRILL) | Tucson, Arizona, United States | Estimated | 2009 | 450 | Linear Foot (LF) | 2009 | $50.00 |  |  | View Details |
| Conduit Design and Installation - Corridor | Conduit | ELECTRICAL CONDUIT (2-3" HDPE, DIRECTIONAL DRILL) | Tucson, Arizona, United States | Estimated | 2009 | 450 | Linear Foot (LF) | 2009 | $38.00 | | | View Details |
| Conduit Design and Installation - Corridor | Conduit | ELECTRICAL CONDUIT (2-3" HDPE, DIRECTIONAL DRILL) | Tucson, Arizona, United States | Estimated | 2009 | 450 | Linear Foot (LF) | 2009 | $29.00 |  |  | View Details |
| Conduit Design and Installation - Corridor | Conduit | ELECTRICAL CONDUIT (2-3" HDPE, DIRECTIONAL DRILL) | Tucson, Arizona, United States | Estimated | 2009 | 450 | Linear Foot (LF) | 2009 | $31.50 | | | View Details |
| Conduit Design and Installation - Corridor | Conduit | ELECTRICAL CONDUIT (2-3" HDPE, DIRECTIONAL DRILL) | Tucson, Arizona, United States | Estimated | 2009 | 450 | Linear Foot (LF) | 2009 | $45.00 |  |  | View Details |
| Conduit Design and Installation - Corridor | Conduit | ELECTRICAL CONDUIT (2-3" HDPE, DIRECTIONAL DRILL) | Tucson, Arizona, United States | Estimated | 2009 | 450 | Linear Foot (LF) | 2009 | $16.39 | | | View Details |
| Conduit Design and Installation - Corridor | Conduit | ELECTRICAL CONDUIT (3-3" HDPE, DIRECTIONAL DRILL) | Tucson, Arizona, United States | Estimated | 2009 |  | Per Mile | 2009 | $211,200.00 |  |  | View Details |
| Conduit Design and Installation - Corridor | Conduit | ELECTRICAL CONDUIT (3-3" HDPE, DIRECTIONAL DRILL) | Tucson, Arizona, United States | Actual | 2009 | | Per Mile | 2009 | $103,488.00 | | | View Details |
| Conduit Design and Installation - Corridor | Conduit | ELECTRICAL CONDUIT (3-3" HDPE, DIRECTIONAL DRILL) | Tucson, Arizona, United States | Estimated | 2009 |  | Per Mile | 2009 | $111,091.20 |  |  | View Details |
| Conduit Design and Installation - Corridor | Conduit | ELECTRICAL CONDUIT (3-3" HDPE, DIRECTIONAL DRILL) | Tucson, Arizona, United States | Estimated | 2009 | | Per Mile | 2009 | $137,280.00 | | | View Details |
| Conduit Design and Installation - Corridor | Conduit | ELECTRICAL CONDUIT (3-3" HDPE, DIRECTIONAL DRILL) | Tucson, Arizona, United States | Estimated | 2009 |  | Per Mile | 2009 | $142,560.00 |  |  | View Details |
| Conduit Design and Installation - Corridor | Conduit | ELECTRICAL CONDUIT (3-3" HDPE, DIRECTIONAL DRILL) | Tucson, Arizona, United States | Estimated | 2009 | | Per Mile | 2009 | $132,000.00 | | | View Details |
| Conduit Design and Installation - Corridor | Conduit | ELECTRICAL CONDUIT (3-3" HDPE, DIRECTIONAL DRILL) | Tucson, Arizona, United States | Estimated | 2009 |  | Per Mile | 2009 | $147,840.00 |  |  | View Details |
| Conduit Design and Installation - Corridor | Conduit | ELECTRICAL CONDUIT (3-3" HDPE, DIRECTIONAL DRILL) | Tucson, Arizona, United States | Estimated | 2009 | | Per Mile | 2009 | $132,000.00 | | | View Details |
| Conduit Design and Installation - Corridor | Conduit | ELECTRICAL CONDUIT (3-3" HDPE, DIRECTIONAL DRILL) | Tucson, Arizona, United States | Estimated | 2009 |  | Per Mile | 2009 | $79,992.00 |  |  | View Details |
| Conduit Design and Installation - Corridor | Conduit | ELECTRICAL CONDUIT (4-3") (HDPE, DIRECTIONAL DRILL) | Tucson, Arizona, United States | Estimated | 2009 | | Per Mile | 2009 | $227,040.00 | | | View Details |
| Conduit Design and Installation - Corridor | Conduit | ELECTRICAL CONDUIT (4-3") (HDPE, DIRECTIONAL DRILL) | Tucson, Arizona, United States | Actual | 2009 |  | Per Mile | 2009 | $115,104.00 |  |  | View Details |
| Conduit Design and Installation - Corridor | Conduit | ELECTRICAL CONDUIT (4-3") (HDPE, DIRECTIONAL DRILL) | Tucson, Arizona, United States | Estimated | 2009 | | Per Mile | 2009 | $146,097.60 | | | View Details |
| Conduit Design and Installation - Corridor | Conduit | ELECTRICAL CONDUIT (4-3") (HDPE, DIRECTIONAL DRILL) | Tucson, Arizona, United States | Estimated | 2009 |  | Per Mile | 2009 | $168,960.00 |  |  | View Details |
| Conduit Design and Installation - Corridor | Conduit | ELECTRICAL CONDUIT (4-3") (HDPE, DIRECTIONAL DRILL) | Tucson, Arizona, United States | Estimated | 2009 | | Per Mile | 2009 | $163,680.00 | | | View Details |
| Conduit Design and Installation - Corridor | Conduit | ELECTRICAL CONDUIT (4-3") (HDPE, DIRECTIONAL DRILL) | Tucson, Arizona, United States | Estimated | 2009 |  | Per Mile | 2009 | $158,400.00 |  |  | View Details |
| Conduit Design and Installation - Corridor | Conduit | ELECTRICAL CONDUIT (4-3") (HDPE, DIRECTIONAL DRILL) | Tucson, Arizona, United States | Estimated | 2009 | | Per Mile | 2009 | $174,240.00 | | | View Details |
| Conduit Design and Installation - Corridor | Conduit | ELECTRICAL CONDUIT (4-3") (HDPE, DIRECTIONAL DRILL) | Tucson, Arizona, United States | Estimated | 2009 |  | Per Mile | 2009 | $211,200.00 |  |  | View Details |
| Conduit Design and Installation - Corridor | Conduit | ELECTRICAL CONDUIT (4-3") (HDPE, DIRECTIONAL DRILL) | Tucson, Arizona, United States | Estimated | 2009 | | Per Mile | 2009 | $117,427.20 | | | View Details |
| Conduit Design and Installation - Corridor | Conduit | ELECTRICAL CONDUIT (4-3" RMC) | Tucson, Arizona, United States | Estimated | 2009 | 800 | Linear Foot (LF) | 2009 | $70.00 |  |  | View Details |
| Conduit Design and Installation - Corridor | Conduit | ELECTRICAL CONDUIT (4-3" RMC) | Tucson, Arizona, United States | Actual | 2009 | 800 | Linear Foot (LF) | 2009 | $94.20 | | | View Details |
| Conduit Design and Installation - Corridor | Conduit | ELECTRICAL CONDUIT (4-3" RMC) | Tucson, Arizona, United States | Estimated | 2009 | 800 | Linear Foot (LF) | 2009 | $53.53 |  |  | View Details |
| Conduit Design and Installation - Corridor | Conduit | ELECTRICAL CONDUIT (4-3" RMC) | Tucson, Arizona, United States | Estimated | 2009 | 800 | Linear Foot (LF) | 2009 | $57.00 | | | View Details |
| Conduit Design and Installation - Corridor | Conduit | ELECTRICAL CONDUIT (4-3" RMC) | Tucson, Arizona, United States | Estimated | 2009 | 800 | Linear Foot (LF) | 2009 | $90.00 |  |  | View Details |
| Conduit Design and Installation - Corridor | Conduit | ELECTRICAL CONDUIT (4-3" RMC) | Tucson, Arizona, United States | Estimated | 2009 | 800 | Linear Foot (LF) | 2009 | $58.00 | | | View Details |
| Conduit Design and Installation - Corridor | Conduit | ELECTRICAL CONDUIT (4-3" RMC) | Tucson, Arizona, United States | Estimated | 2009 | 800 | Linear Foot (LF) | 2009 | $67.00 |  |  | View Details |
| Conduit Design and Installation - Corridor | Conduit | ELECTRICAL CONDUIT (4-3" RMC) | Tucson, Arizona, United States | Estimated | 2009 | 800 | Linear Foot (LF) | 2009 | $241.00 | | | View Details |
| Conduit Design and Installation - Corridor | Conduit | ELECTRICAL CONDUIT (4-3" RMC) | Tucson, Arizona, United States | Estimated | 2009 | 800 | Linear Foot (LF) | 2009 | $118.56 |  |  | View Details |
| Conduit Design and Installation - Corridor | Conduit | ELECTRICAL CONDUIT (3" HDPE) (DIRECTIONAL DRILL) | Tucson, Arizona, United States | Estimated | 2009 | 705 | Linear Foot (LF) | 2009 | $27.00 | | | View Details |
| Conduit Design and Installation - Corridor | Conduit | ELECTRICAL CONDUIT (3" HDPE) (DIRECTIONAL DRILL) | Tucson, Arizona, United States | Actual | 2009 | 705 | Linear Foot (LF) | 2009 | $10.40 |  |  | View Details |
| Conduit Design and Installation - Corridor | Conduit | ELECTRICAL CONDUIT (3" HDPE) (DIRECTIONAL DRILL) | Tucson, Arizona, United States | Estimated | 2009 | 705 | Linear Foot (LF) | 2009 | $16.16 | | | View Details |
| Conduit Design and Installation - Corridor | Conduit | ELECTRICAL CONDUIT (3" HDPE) (DIRECTIONAL DRILL) | Tucson, Arizona, United States | Estimated | 2009 | 705 | Linear Foot (LF) | 2009 | $17.00 |  |  | View Details |
| Conduit Design and Installation - Corridor | Conduit | ELECTRICAL CONDUIT (3" HDPE) (DIRECTIONAL DRILL) | Tucson, Arizona, United States | Estimated | 2009 | 705 | Linear Foot (LF) | 2009 | $21.00 | | | View Details |
| Conduit Design and Installation - Corridor | Conduit | ELECTRICAL CONDUIT (3" HDPE) (DIRECTIONAL DRILL) | Tucson, Arizona, United States | Estimated | 2009 | 705 | Linear Foot (LF) | 2009 | $16.00 |  |  | View Details |
| Conduit Design and Installation - Corridor | Conduit | ELECTRICAL CONDUIT (3" HDPE) (DIRECTIONAL DRILL) | Tucson, Arizona, United States | Estimated | 2009 | 705 | Linear Foot (LF) | 2009 | $17.00 | | | View Details |
| Conduit Design and Installation - Corridor | Conduit | ELECTRICAL CONDUIT (3" HDPE) (DIRECTIONAL DRILL) | Tucson, Arizona, United States | Estimated | 2009 | 705 | Linear Foot (LF) | 2009 | $23.00 |  |  | View Details |
| Conduit Design and Installation - Corridor | Conduit | ELECTRICAL CONDUIT (3" HDPE) (DIRECTIONAL DRILL) | Tucson, Arizona, United States | Estimated | 2009 | 705 | Linear Foot (LF) | 2009 | $14.34 | | | View Details |
| Conduit Design and Installation - Corridor | Conduit | ELECTRICAL CONDUIT (3-3") (PVC) (OR HDPE) | Tucson, Arizona, United States | Estimated | 2009 |  | Per Mile | 2009 | $163,680.00 |  |  | View Details |
| Conduit Design and Installation - Corridor | Conduit | ELECTRICAL CONDUIT (3-3") (PVC) (OR HDPE) | Tucson, Arizona, United States | Actual | 2009 | | Per Mile | 2009 | $35,904.00 | | | View Details |
| Conduit Design and Installation - Corridor | Conduit | ELECTRICAL CONDUIT (3-3") (PVC) (OR HDPE) | Tucson, Arizona, United States | Estimated | 2009 |  | Per Mile | 2009 | $44,774.40 |  |  | View Details |
| Conduit Design and Installation - Corridor | Conduit | ELECTRICAL CONDUIT (3-3") (PVC) (OR HDPE) | Tucson, Arizona, United States | Estimated | 2009 | | Per Mile | 2009 | $42,240.00 | | | View Details |
| Conduit Design and Installation - Corridor | Conduit | ELECTRICAL CONDUIT (3-3") (PVC) (OR HDPE) | Tucson, Arizona, United States | Estimated | 2009 |  | Per Mile | 2009 | $89,760.00 |  |  | View Details |
| Conduit Design and Installation - Corridor | Conduit | ELECTRICAL CONDUIT (3-3") (PVC) (OR HDPE) | Tucson, Arizona, United States | Estimated | 2009 | | Per Mile | 2009 | $63,360.00 | | | View Details |
| Conduit Design and Installation - Corridor | Conduit | ELECTRICAL CONDUIT (3-3") (PVC) (OR HDPE) | Tucson, Arizona, United States | Estimated | 2009 |  | Per Mile | 2009 | $72,600.00 |  |  | View Details |
| Conduit Design and Installation - Corridor | Conduit | ELECTRICAL CONDUIT (3-3") (PVC) (OR HDPE) | Tucson, Arizona, United States | Estimated | 2009 | | Per Mile | 2009 | $132,000.00 | | | View Details |
| Conduit Design and Installation - Corridor | Conduit | ELECTRICAL CONDUIT (3-3") (PVC) (OR HDPE) | Tucson, Arizona, United States | Estimated | 2009 |  | Per Mile | 2009 | $57,710.40 |  |  | View Details |
| Conduit Design and Installation - Corridor | Conduit | ELECTRICAL CONDUIT (4-3") (PVC) (OR HDPE) | Tucson, Arizona, United States | Estimated | 2009 | | Per Mile | 2009 | $200,640.00 | | | View Details |
| Conduit Design and Installation - Corridor | Conduit | ELECTRICAL CONDUIT (4-3") (PVC) (OR HDPE) | Tucson, Arizona, United States | Actual | 2009 |  | Per Mile | 2009 | $40,128.00 |  |  | View Details |
| Conduit Design and Installation - Corridor | Conduit | ELECTRICAL CONDUIT (4-3") (PVC) (OR HDPE) | Tucson, Arizona, United States | Estimated | 2009 | | Per Mile | 2009 | $49,051.20 | | | View Details |
| Conduit Design and Installation - Corridor | Conduit | ELECTRICAL CONDUIT (4-3") (PVC) (OR HDPE) | Tucson, Arizona, United States | Estimated | 2009 |  | Per Mile | 2009 | $47,520.00 |  |  | View Details |
| Conduit Design and Installation - Corridor | Conduit | ELECTRICAL CONDUIT (4-3") (PVC) (OR HDPE) | Tucson, Arizona, United States | Estimated | 2009 | | Per Mile | 2009 | $52,800.00 | | | View Details |
| Conduit Design and Installation - Corridor | Conduit | ELECTRICAL CONDUIT (4-3") (PVC) (OR HDPE) | Tucson, Arizona, United States | Estimated | 2009 |  | Per Mile | 2009 | $68,640.00 |  |  | View Details |
| Conduit Design and Installation - Corridor | Conduit | ELECTRICAL CONDUIT (4-3") (PVC) (OR HDPE) | Tucson, Arizona, United States | Estimated | 2009 | | Per Mile | 2009 | $73,920.00 | | | View Details |
| Conduit Design and Installation - Corridor | Conduit | ELECTRICAL CONDUIT (4-3") (PVC) (OR HDPE) | Tucson, Arizona, United States | Estimated | 2009 |  | Per Mile | 2009 | $73,920.00 |  |  | View Details |
| Conduit Design and Installation - Corridor | Conduit | ELECTRICAL CONDUIT (4-3") (PVC) (OR HDPE) | Tucson, Arizona, United States | Estimated | 2009 | | Per Mile | 2009 | $62,832.00 | | | View Details |
| Conduit Design and Installation - Corridor | Conduit and Cable Installation | Total Installation Cost (Trawick Construction = $333,339.31), (Duke Power = $11,699.38), (BellSouth = $6,711.03), (CSX Wireline Fee = $14,350). | Charlotte, North Carolina, USA | Actual | 2004 |  | Lump Sum (LS) | 2004 | $366,099.00 |  | 30 | View Details |
| Conduit Design and Installation - Corridor | Conduit Boring | Boring under streets and driveways. Design not included. | Laredo, Texas, USA | Actual | 2003 | | Linear Foot (LF) | 2003 | $127.70 | | 20 | View Details |
| Conduit Design and Installation - Corridor | Conduit Design - Corridor | Total design cost by CBW. | Charlotte, North Carolina, USA | Actual | 2004 |  | Each (EA) | 2004 | $326,760.00 |  | 30 | View Details |
| Conduit Design and Installation - Corridor | Conduit Design and Installation - Corridor | Ground installation. | Raleigh, North Carolina, USA | Actual | 2003 | 5.7 | Per Mile | 2003 | $37,000.00 | | 20 | View Details |
| Conduit Design and Installation - Corridor | Conduit Design and Installation - Corridor | Aerial conduit installation to connect Burlington and Greensboro. | Burlington, North Carolina, USA,Greensboro, North Carolina, USA | Actual | 2004 |  | Per Mile | 2004 | $2,900.00 |  | 20 | View Details |
| Conduit Design and Installation - Corridor | Conduit Design and Installation - Corridor | In-ground conduit installation to connect Burlington and Greensboro. | Burlington, North Carolina, USA,Greensboro, North Carolina, USA | Actual | 2004 | | Per Mile | 2004 | $40,000.00 | | 20 | View Details |
| Conduit Design and Installation - Corridor | Conduit Design and Installation - Corridor | Conduit from Transportation building to Administration building. | Durham, North Carolina, USA | Actual | 2005 |  | Per Mile | 2005 | $59,700.00 |  | 20 | View Details |
| Conduit Design and Installation - Corridor | Conduit Design and Installation - Corridor | Includes potholing, traffic control, cleanup, 2 inch conduit purchase/install, 18x30 and 30x48 vaults, and mobilization. | Fort Collins, Colorado, USA | Actual | 2003 | | Per Mile | 2003 | $21,800.00 | | | View Details |
| Conduit Design and Installation - Corridor | Conduit Design and Installation - Corridor | Conduit design and installation. | Fort Collins, Colorado, USA | Actual | 2005 |  | Per Mile | 2005 | $54,300.00 |  | 20 | View Details |
| Conduit Design and Installation - Corridor | Conduit Design and Installation - Corridor | Included combined cost of boring, trenching, and conduit. Conduit was 4-inch multi-duct conduit with three 1.5-inch interior ducts. Design was done in-house and was not reflected in capital costs. | Fort Worth, Texas, USA | Actual | 2003 | | Per Mile | 2003 | $55,014.00 | $1,000.00 | 20 | View Details |
| Conduit Design and Installation - Corridor | Conduit Design and Installation - Corridor | PVC Conduit | Portland, Oregon, USA | Actual | 2003 |  | Per Mile | 2003 | $64,000.00 |  | 30 | View Details |
| Conduit Design and Installation - Corridor | Conduit Design and Installation - Corridor | Conduit design and installation. | Houston, Texas, USA | Unknown | 2000 | | Per Mile | 2000 | $32,000.00 | $4,000.00 | 10 | View Details |
| Conduit Design and Installation - Corridor | Conduit Design and Installation - Corridor | Conduit design and installation, including pullboxes. | Charlotte, North Carolina, USA | Actual | 2004 |  | Per Mile | 2004 | $76,000.00 |  | 30 | View Details |
| Conduit Design and Installation - Corridor | Conduit Design and Installation - Corridor | Conduit design and installation. | Charlotte, North Carolina, USA | Actual | 2006 | | Per Mile | 2006 | $75,800.00 | | 20 | View Details |
| Conduit Design and Installation - Corridor | Conduit Design and Installation - Corridor | Includes the design costs and installation. | North Carolina, USA | Estimated | 2004 |  | Per Mile | 2004 | $75,200.00 |  | 20 | View Details |
| Conduit Design and Installation - Corridor | Conduit Design and Installation - Corridor | Includes the design costs and installation. | North Carolina, USA | Estimated | 2004 | | Per Mile | 2004 | $101,900.00 | | 20 | View Details |
| Conduit Design and Installation - Corridor | Conduit Design and Installation - Corridor | Conduit design and installation. $50k per mile cost is normal; $100k possible in dense urban areas; $250k possible for rock or in-shoulder installation in mountains. | Colorado, USA | Actual | 2005 |  | Per Mile | 2005 | $50,000.00 |  | 20 | View Details |
| Conduit Design and Installation - Corridor | Conduit Design and Installation - Corridor | Includes directional bores and conduit excavation and restoration. | Tukwila, Washington, USA | Estimated | 2006 | | Per Mile | 2006 | $414,100.00 | $2,070.00 | 10 | View Details |
| Conduit Design and Installation - Corridor | Conduit Design and Installation - Corridor | Conduit design and installation. | Blaine, Washington, USA | Estimated | 2006 |  | Per Mile | 2006 | $85,000.00 | $100.00 | 50 | View Details |
| Conduit Design and Installation - Corridor | Conduit Design and Installation - Corridor | Total cost of conduit design and installation on corridor. | North Carolina, USA | Actual | 2004 | | Per Mile | 2004 | $73,440.00 | | 20 | View Details |
| Conduit Design and Installation - Corridor | Conduit Design and Installation - Corridor | Conduit design and installation - corridor. | Hattiesburg, Mississippi, USA | Actual | 2004 |  | Per Mile | 2004 | $95,000.00 | $1,000.00 | 30 | View Details |
| Conduit Design and Installation - Corridor | Conduit Design and Installation - Corridor | 1.5-inch PVC Sch.40 plastic conduit bored and trenched; 3-inch PVC Sch.40 plastic conduit trenched. Includes installation and conduit. | Tulsa, Oklahoma, USA | Estimated | 2004 | | Per Mile | 2004 | $16,200.00 | | | View Details |
| Conduit Design and Installation - Corridor | Conduit Design and Installation - Corridor | 1.5-inch Sch.40 PVC conduit, bored and trenched. Includes installation and conduit. | Oklahoma City, Oklahoma, USA | Actual | 2004 |  | Per Mile | 2004 | $65,400.00 |  |  | View Details |
| Conduit Design and Installation - Corridor | Conduit Design and Installation - Corridor | 1.5-inch PVC Sch.40 conduit bored and trenched. Includes installation and conduit. High cost is a result of short conduit run (Approx. 500 feet). | Oklahoma City, Oklahoma, USA | Actual | 2004 | | Per Mile | 2004 | $124,300.00 | | | View Details |
| Conduit Design and Installation - Corridor | Conduit Design and Installation - Corridor | 1.5-inch PVC Sch.40 plastic conduit bored and trenched. Includes installation and conduit. | Oklahoma City, Oklahoma, USA | Estimated | 2004 |  | Per Mile | 2004 | $14,400.00 |  |  | View Details |
| Conduit Design and Installation - Corridor | Conduit Design and Installation - Corridor | Conduit design and installation - corridor. | Lynnwood, Washington, USA | Actual | 2005 | | Per Mile | 2004 | $191,000.00 | $3,000.00 | 50 | View Details |
| Conduit Design and Installation - Corridor | Conduit Design and Installation - Corridor | Includes material, labor and installation. | Edmonds, Washington, USA,Mukilteo, Washington, USA,and Anacortes, Washington, USA | Estimated | 2001 |  | Per Mile | 2001 | $43,068.00 | $0.00 | 20 | View Details |
| Conduit Design and Installation - Corridor | Conduit Innerduct | Cable Innerduct (1 inch) for Fiber Optic Cable | Phoenix, Arizona, USA | Estimated | 2009 | | Per Mile | 2009 | $10,560.00 | | | View Details |
| Conduit Design and Installation - Corridor | Conduit Innerduct | Cable Innerduct (1 inch) for Fiber Optic Cable | Phoenix, Arizona, USA | Actual | 2009 |  | Per Mile | 2009 | $5,280.00 |  |  | View Details |
| Conduit Design and Installation - Corridor | Conduit Innerduct | Cable Innerduct (1 inch) for Fiber Optic Cable | Phoenix, Arizona, USA | Actual | 2009 | | Per Mile | 2009 | $6,072.00 | | | View Details |
| Conduit Design and Installation - Corridor | Conduit Innerduct | Cable Innerduct (1 inch) for Fiber Optic Cable | Phoenix, Arizona, USA | Actual | 2009 |  | Per Mile | 2009 | $10,560.00 |  |  | View Details |
| Conduit Design and Installation - Corridor | Conduit Innerduct | Cable Innerduct (1 inch) for Fiber Optic Cable | Phoenix, Arizona, USA | Actual | 2009 | | Per Mile | 2009 | $6,864.00 | | | View Details |
| Conduit Design and Installation - Corridor | Conduit Innerduct | Cable Innerduct (1 inch) for Fiber Optic Cable | Phoenix, Arizona, USA | Actual | 2009 |  | Per Mile | 2009 | $8,553.60 |  |  | View Details |
| Conduit Design and Installation - Corridor | Conduit Innerduct | CABLE INNERDUCT (1") | Tucson, Arizona, United States | Estimated | 2009 | | Per Mile | 2009 | $10,560.00 | | | View Details |
| Conduit Design and Installation - Corridor | Conduit Innerduct | CABLE INNERDUCT (1") | Tucson, Arizona, United States | Actual | 2009 |  | Per Mile | 2009 | $3,168.00 |  |  | View Details |
| Conduit Design and Installation - Corridor | Conduit Innerduct | CABLE INNERDUCT (1") | Tucson, Arizona, United States | Estimated | 2009 | | Per Mile | 2009 | $4,118.40 | | | View Details |
| Conduit Design and Installation - Corridor | Conduit Innerduct | CABLE INNERDUCT (1") | Tucson, Arizona, United States | Estimated | 2009 |  | Per Mile | 2009 | $6,336.00 |  |  | View Details |
| Conduit Design and Installation - Corridor | Conduit Innerduct | CABLE INNERDUCT (1") | Tucson, Arizona, United States | Estimated | 2009 | | Per Mile | 2009 | $4,488.00 | | | View Details |
| Conduit Design and Installation - Corridor | Conduit Innerduct | CABLE INNERDUCT (1") | Tucson, Arizona, United States | Estimated | 2009 |  | Per Mile | 2009 | $5,280.00 |  |  | View Details |
| Conduit Design and Installation - Corridor | Conduit Innerduct | CABLE INNERDUCT (1") | Tucson, Arizona, United States | Estimated | 2009 | | Per Mile | 2009 | $4,488.00 | | | View Details |
| Conduit Design and Installation - Corridor | Conduit Innerduct | CABLE INNERDUCT (1") | Tucson, Arizona, United States | Estimated | 2009 |  | Per Mile | 2009 | $3,960.00 |  |  | View Details |
| Conduit Design and Installation - Corridor | Conduit Innerduct | CABLE INNERDUCT (1") | Tucson, Arizona, United States | Estimated | 2009 | | Per Mile | 2009 | $6,336.00 | | | View Details |
| Conduit Design and Installation - Corridor | Conduit installation | Conduit, furnish & install, aboveground | Florida, United States | Estimated | 2013 |  | Linear Foot (LF) | 2013 | $7.98 |  |  | View Details |
| Conduit Design and Installation - Corridor | Conduit installation | Conduit, furnish & install, underground | Florida, United States | Estimated | 2013 | | Linear Foot (LF) | 2013 | $2.33 | | | View Details |
| Conduit Design and Installation - Corridor | Conduit installation | Conduit, furnish & install, under existing pavement sawcut | Florida, United States | Estimated | 2013 |  | Linear Foot (LF) | 2013 | $21.51 |  |  | View Details |
| Conduit Design and Installation - Corridor | Conduit installation | Conduit, install, underground | Florida, United States | Estimated | 2013 | | Linear Foot (LF) | 2013 | $2.00 | | | View Details |
| Conduit Design and Installation - Corridor | Conduit installation | Conduit, install, under existing pavement sawcut | Florida, United States | Estimated | 2013 |  | Linear Foot (LF) | 2013 | $3.00 |  |  | View Details |
| Conduit Design and Installation - Corridor | Conduit junction box | Pull & junction box, furnish & install | Florida, United States | Estimated | 2013 | | Each (EA) | 2013 | $569.87 | | | View Details |
| Conduit Design and Installation - Corridor | Conduit pull box | Pull box for fiber optic cable, furnish & install | Florida, United States | Estimated | 2013 |  | Each (EA) | 2013 | $992.18 |  |  | View Details |
| Conduit Design and Installation - Corridor | Conduit splice box | Splice box for fiber optic cable, furnish & install | Florida, United States | Estimated | 2013 | | Each (EA) | 2013 | $2,114.30 | | | View Details |
| Conduit Design and Installation - Corridor | Conduit Trenching | Digging/filling trenches. Design not included. | Laredo, Texas, USA | Actual | 2003 |  | Linear Foot (LF) | 2003 | $73.60 |  | 20 | View Details |